Individual Project
1. A project has been defined to contain the following list of activities along with their required times for completion.
|
Activity No. |
Activity |
Time (weeks) |
Immediate Predecessors |
|
1 A |
Collect requirements |
3 |
|
|
2 B |
Analyze processes |
2 |
1 A |
|
3 C |
Analyze data |
2 |
2 B |
|
4 D |
Design processes |
6 |
2 B |
|
5 E |
Design data |
3 |
3 C |
|
6 F |
Design screens |
2 |
3,4 C,D |
|
7 G |
Design reports |
4 |
4,5 D,E |
|
8 H |
Program |
5 |
6,7 E,F |
|
9 I |
Test and Document |
7 |
7 G |
|
10 J |
Install |
2 |
8,9 H,I |
A. Draw a network diagram for the activities.
B. Calculate the earliest expected completion time.
C. Show the critical path.
D. What would have if activity 6 were revised to take six weeks instead of two weeks?